Our House in Norfolk

 

 

 

May 2015 update

Another six months have passed. Three bathrooms have been installed (one more to go), the beautiful bespoke kitchen has been installed by Jem Lake Kitchens Ltd, the stairs are in complete with bannister and the glass balustrade has been added to the balcony.

 

Stairs

Kitchen 1

Kitchen 2

Balcony

What a difference the plasterer makes!

Things are moving very rapidly.

Outside the patio has been laid using Indian limestone.IMG_1209

 

IMG_4412

IMG_4410

 

 

 

 

 

 

 

Inside two hundred sheets have been fixed to the walls and ceilings. The decorator applied the first coat of paint as soon as the plaster was dry in the kitchen/living area transforming it from a building site to a beautiful room.

IMG_4394

And the bedrooms start to take shape too.

And the bedrooms too

 

Work continues apace in other areas too. The solar panels have been connected,first fix plumbing and electrics are completed. The “plant room” is starting to resemble the bridge of the Starship Enterprize and we haven’t even started on the air source heat pump yet.

IMG_1367Underfloor heating is being laid throughout the ground floor in preparation for the Flow screed to be pumped at the beginning of October. It will finally be safe to walk on the floors without fear of falling through the polystyrene insulation between the beams!

 

IMG_1368

 

Three months later

IMG_1067

 

I haven’t written anything for sometime,not because nothing has happened but because there hasn’t been anything to photograph.

Outside the cladding (cement fibre based cladding that never needs painting or maintenance) has been applied to the balcony and porch leaving a space for a small window for that all important sea view.

The windows finally arrived after eight weeks but were well worth the wait, powder coated aluminium in peppermint green. They look fantastic and integral blinds in the bifold doors and upstairs bedroom mean privacy and shade are ensured.

IMG_1063

Meanwhile inside, the first fix electric is nearly completed with miles of cables snaking in and out of the walls and joists.

One hundred millimetre thick insulation between the joists and fifty millimetre on top mean the the plater board has had to be secured by four inch screws!

 

IMG_1053

 

 

Work on the roof

On the 26th September the glulam beams arrive so that work can begin on the roof.  The quarter ton, eleven metre beam was manhandled into place by Stuart and his men.

IMG-20130926-00065IMG-20130926-00070                                                     That’s the first one in place only another ten to go!

The hand cut roof takes shape, a veritable forest of wood.

IMG_0948

 

IMG_0930IMG_0951

 

 

 

 

 

 

 

When complete, sterling board is nailed on to add strength to the structure.


IMG_0945
IMG_0934

First floor joists

First floor joists

 

We have used Easy joists which are made up of a 3×2 batten top and bottom held together with a metal webbing.

We are hoping to eliminate some of the creaking associated with solid wood joists but the biggest advantage is the ability to run all the services including 4 inch soil pipes through the joists.

 

IMG_4225

IMG-20130917-00062

 

 

 

 

 

 

IMG-20130917-00058